To replace a roof that has solar panels, the panels and their mounting hardware come off first and go back on after the new roof is finished, a job often called detach and reset. It is a separate piece of work from the roofing. Of the two Colorado building departments we checked, Pikes Peak Regional requires building and electrical permits on top of the roofing permit, and Broomfield's reinstallation form names an electrician and a state license number. Whether insurance pays for it, and what it does to the roof warranty and the solar warranties, depends on your policy and on the warranty documents you hold.

This page explains how the job generally works and what to ask. It is not legal or insurance advice. Permit rules are set by your city or county, and warranty terms by the companies that issued them.

Do solar panels have to come off for a new roof?

Yes. The U.S. Department of Energy puts it in one sentence: “During a roof replacement, the solar panels and mounting system will need to be removed to complete the work” (U.S. Department of Energy, 2024). The mounts are fastened through the roof covering into the structure, so the old shingles cannot be torn off around them.

It is not a small job. A National Renewable Energy Laboratory working group describes it plainly: “the cost of removing and re-installing a PV array is high and also entails lost production” (NREL, Best Practices for Operation and Maintenance, 2018). We found no primary source that publishes a typical price, so this page does not give one. Get the figure in writing from whoever will do the work.

Who removes and reinstalls the panels?

Plan on an electrician or a solar contractor being involved. A solar array is an electrical system, and the two Colorado building department documents we read both point that way:

  • The Pikes Peak Regional Building Department in Colorado Springs “requires both a building permit and an electrical permit for Solar Photo Voltaic Systems that are removed and re-installed when a re-roof is taking place, in addition to a roofing permit” (Pikes Peak Regional Building Department).
  • Broomfield's Building Division has a Solar PV Reinstallation Affidavit that names the electrician and a state license number and is signed by the electrician and the homeowner (City and County of Broomfield).

That leaves three possible arrangements: the company that installed the system does it, another solar contractor does it, or the roofer hires and coordinates a solar contractor. None is right for every house. What matters is that one named company holds whatever permit your building department requires for the solar work, and that you know whether your solar warranties care who touches the equipment (see the warranty section below). If your system is leased or under a power purchase agreement, you do not own the equipment: read the agreement and call that company before you sign a roofing contract.

What permits does it take in Colorado?

That is set by your city or county, and Colorado building departments do not all handle it the same way. The two we read show the range:

  • Pikes Peak Regional Building Department:a building permit and an electrical permit for the solar work, plus the roofing permit. For an older system with no permit history on file, it “will require a pre inspection prior to the removal of the Solar System to document what is installed.” It also states that it “is not requiring any of these older systems to be brought up to current codes when re-installed,” and that panels “must be remounted in a manner that is equal to or better than the original installation.”
  • Broomfield:the reinstallation affidavit states: “The system will not be altered in any way including but not limited to: Repairing, adding, removing, or relocating of any elements of the system.” The signed affidavit “will be accepted in lieu of a Final Inspection.”

Both documents make the same practical point: putting the same system back the same way is treated differently from changing it. If you plan to add panels, swap inverters or move the array while it is down, ask whether that needs a full solar permit. Call your own building department before work is scheduled; our service area pages cover roofing permits city by city. Ask your electric utility, too, whether it needs notice before the system is shut down and switched back on.

What is the usual order of work?

The order follows from the permits. Using the Pikes Peak department's written process as the model:

  1. Document the system as it sits. Photos of the layout, the equipment labels and the wiring, and a pre-removal inspection where the building department asks for one.
  2. Pull the permits. Roofing, plus whatever your jurisdiction requires for the solar work.
  3. Shut down and remove the panels, racking and mounts, and store them where they will not be damaged.
  4. Replace the roof.This is the moment to fix anything under the array. The Department of Energy suggests asking a roofer about “replacing protruding vent pipes with low-profile vent openings, which can fit underneath solar panels” (U.S. Department of Energy, 2021).
  5. Pass the roofing inspection before the panels go back. Pikes Peak: “A minimum of one inspection is required to be performed on the re-roof permit prior to solar panels being re-installed.”
  6. Reinstall, seal every mount, and close out the solar permit.NREL's installation guide lists this among the basics: “Appropriate weather sealing of all penetrations of the building envelope” ( NREL, Best Practices in PV System Installation, 2015).

The system produces nothing between steps 3 and 6. Ask both contractors for dates, and ask what happens to the schedule if the roofing inspection is delayed.

Does removing the panels affect my roof warranty?

In the three shingle warranties we read, the manufacturer covers its shingles, not the cost or the consequences of what is mounted on them. In alphabetical order:

  • CertainTeed:“Costs associated with removal or replacement of overburden (items installed over the shingles, including but not limited to, solar panels, satellite dishes and gardens) are the sole responsibility of the property owner” (2026 limited warranty).
  • Owens Corning:“Owens Corning will not compensate for the removal and replacement of solar panels or other rooftop equipment,” and its list of what is not covered includes: “Damage to the Roofing System caused by alterations made after completion of application, including structural changes, equipment, or solar panel installation” (Platinum Protection limited warranty).
  • TAMKO:its exclusions do not mention solar by name, but they include “damage by traffic on the roof” and: “Leaks or damage to the Shingles from any cause other than an inherent manufacturing defect in the Shingles” (limited warranty effective November 1, 2026).

In plain terms: if a shingle turns out to be defective under an array, expect to pay for getting the panels off and back on; and under terms like these a leak at a solar mount is unlikely to be the shingle maker's to fix. The roofer's own workmanship warranty is a separate document. NREL notes that such a warranty “will typically cover leakage or total failure but not wear-and-tear or damage associated with the PV system.” Other brands and other warranty tiers word this differently, so read the warranty for the product going on your roof, and get in writing who is responsible for leaks at the solar mounts after the reinstall.

Does it affect the solar system's warranty?

It can, and the answer is in each warranty you hold: panels, inverters, racking and the installer's workmanship can each have their own warranty. The Department of Energy's installer checklist includes asking “about coverage under warranties if there's a problem with a component or the energy system after installation.”

As one example of what the fine print looks like, Enphase's current U.S. microinverter warranty covers products installed “at the original end user location,” does not apply to “any damage to the Covered Products caused by service performed by anyone who is not a representative of Enphase,” and “does not include any cost of labor related to (i) un-installing Covered Product; (ii) re-installing a repaired or replacement product” ( Enphase limited warranty, 2025). Whether a removal and reinstallation on the same house affects that coverage is for Enphase and your installer to answer, not this page. Other manufacturers' terms differ. Before the panels come down, ask your original installer and the equipment manufacturers, in writing, whether removal and reinstallation by the company you plan to use affects coverage.

Does homeowners insurance pay for removing and resetting the panels?

It depends on your policy, and we found no Colorado statute or Division of Insurance publication that sets a rule. Three questions to settle with your insurer: whether the roof replacement itself is a covered loss, whether your policy covers the solar system, and whether the system is yours or a leasing company's. The National Association of Insurance Commissioners tells homeowners adding solar that “it's important to check with your homeowners insurer” ( NAIC, 2017).

On a hail or wind claim, look for the solar work in the insurer's itemized estimate. If it is not there, ask in writing whether it is covered and send the solar contractor's quote before the work is done. The Colorado Division of Insurance describes how additional damage found during repairs is handled, and we suggest treating a missing solar line the same way: “it is important to provide additional information about this damage to your insurer before allowing repair work to continue. The insurer will review and issue a supplement if approved” ( consumer advisory, May 31, 2024). Hail damage to the panels themselves is a separate question from the cost of moving undamaged panels; ask about each. If the roof is being replaced because of its age, with no covered loss, there is no claim to attach the solar work to. Our guide to what you pay on a hail or wind roof claim covers deductibles, depreciation and supplements.

Should I replace the roof before going solar?

If the roof is near the end of its life, yes. The Department of Energy tells prospective solar owners to “consider the age of your roof and how long until it will need replacement” (Homeowner's Guide to Solar), and NREL's installation guide is more specific: “If the roof covering will need replacement before the end of the expected PV system lifetime (20-25 years), the homeowner should consider roof replacement prior to PV system installation.” Doing the roof first avoids paying for a removal and reinstallation later.

What should I ask before the panels come down?

Ask the roofer:

  • Who removes and reinstalls the solar system: you, a solar contractor you hire, or one I hire? What is that company's name?
  • Is the solar work in your contract price or separate, and who holds the electrical permit?
  • After the reinstall, who is responsible in writing for a leak at a solar mount?
  • Will the roofing inspection be passed before the panels go back on?

Ask the solar contractor:

  • Are you licensed for the electrical work in my city, and will you pull the permit my building department requires?
  • Will the system go back exactly as it was? If any part must change, what does that do to the permit?
  • How will you document the system before removal, and where are the panels stored?
  • What mounts and flashing will you use on the new roof, and are they new?
  • How long will the system be off, and who restarts it and confirms it is producing?
  • What does your workmanship warranty cover after a reinstall?

Ask your insurer, and your solar company if the system is leased or financed:

  • Is removal and reinstallation of the solar system in the estimate? If not, is it covered?
  • Are the panels themselves covered for storm damage, and has anyone inspected them?
  • For a leased system: who may remove it, who pays, and does the agreement keep billing while it is off?

How does Red Hawk Roofing handle a roof with solar?

Ask us before you sign how the solar work would be handled on your roof and by whom, and have the answer written into the contract. Our part is the roof: tear-off, deck inspection, underlayment, flashing and the new roofing, under a 5-year workmanship warranty, as our roof replacement page describes. Who removes and reinstalls the panels on your job is a separate question, and it should be settled in writing before any contract is signed. If the roof is part of a claim, our insurance claim support covers the roofing documentation.

Request a free roof inspection, or call (720) 771-8921.

This guide is general information, not legal, insurance or electrical advice. Your building department, your insurance policy, your solar agreement and the warranty documents for your own equipment control what applies to your home.

Sources

Each source below was opened and read on November 22, 2026. Laws, regulations, product instructions and warranty terms change; the linked document is the authority, not this page.

  1. U.S. Department of Energy, “Should I Replace my Rooftop Solar System?”Dated June 25, 2024; the “Roof replacement” paragraph.
  2. U.S. Department of Energy, Homeowner’s Guide to SolarThe section on whether a roof is suitable for solar.
  3. U.S. Department of Energy, “Decisions, Decisions: Choosing a Solar Installer”Dated August 31, 2021; “Roof Conditions” and the installer questions.
  4. National Renewable Energy Laboratory and others, Best Practices for Operation and Maintenance of Photovoltaic and Energy Storage Systems, 3rd EditionNREL/TP-7A40-73822, December 2018; “Overburden waiver” and “Roof warranty issues”.
  5. Solar Access to Public Capital Working Group (NREL), Best Practices in PV System InstallationVersion 1.0, March 2015; roof condition and weather sealing of penetrations.
  6. Pikes Peak Regional Building Department, solar removal and reinstallation during a re-roofColorado Springs; revision dated October 22, 2025.
  7. City and County of Broomfield, Building Division, Solar PV Reinstallation AffidavitForm revised October 9, 2026.
  8. CertainTeed, Asphalt Shingle Residential Products 2026 Limited WarrantyThe footnote on “overburden”.
  9. Owens Corning, Platinum Protection Limited Lifetime WarrantyPublication 10020608-O, 2026; “Exceptions” and the list of what is not covered.
  10. TAMKO, Fiberglass/Asphalt Shingle Limited WarrantyEdition effective November 1, 2026; “Exclusions from Coverage”.
  11. Enphase Energy, Limited Warranty for IQ Microinverters (U.S., Puerto Rico and Canada)Effective on or after September 1, 2025; sections on the original location, exclusions and labor.
  12. National Association of Insurance Commissioners, “Environmentally-Friendly Insurance”Published July 1, 2017.